Solved:Purchase Orders: Lead time not considered for Delivery Date
04-30-2013, 06:38 AM,
#2
RE: Purchase Orders: Lead time not considered for Delivery Date
The lead time is used for MRP calculations ... but not for purchase order entry.
It would be useful to have this default. However, lead times vary in practice depending on availability ex-stock or whether the item needs to be manufactured and the availability of raw materials for the manufacturer to make... so it may not be appropriate to code this and probably better to make the phone call.
Phil Daintree
webERP Admin
Logic Works Ltd
http://www.logicworks.co.nz
Reply