RE: Work Orders With Multiple Items - Not Working
The requirements are calculated in the WoRealRequirements() function. Looking through this the summing of component parts across the work order was not part of the original functionality but was done at a later date when provision was added for phantom parts. It looks from the comments that a problem was occurring when phantom parts were being dissolved into the BOM.

Now from a quick reading of this, and without actually running trials, it seems it wouldn't be too hard to change for Labour/Overhead parts. The table worequirements has provision for each parent part to have it's own requirements so no DB changes would be needed.

Let me look further.

Tim
Reply


Messages In This Thread
RE: Work Orders With Multiple Items - by phil - 11-27-2018, 05:06 AM
RE: Work Orders With Multiple Items - Not Working - by TimSchofield - 11-28-2018, 01:52 AM

Forum Jump:


Users browsing this thread: 1 Guest(s)