Post Reply 
 
Thread Rating:
  • 0 Votes - 0 Average
  • 1
  • 2
  • 3
  • 4
  • 5
Item Due Date
03-13-2018, 04:58 AM (This post was last modified: 03-13-2018 05:30 AM by phil.)
Post: #5
RE: Item Due Date
No it doesn't work sorry - my dodgy memory!
Needs a fix to CalcEarliestDispatchDate() function in includes/DateFunctions.inc to add this many days to it ... must've intended to use it but never did!


The date it is due - needs to be manually set as this is the customer's requirement and may not be (although mostly I suspect is) ASAP.
If the assumption is ASAP then we would need to look at the preferred supplier lead time from purchdata - if it is setup and if it is a manufactured item we'd need to look at the sum of labour type components x quantity ordered in the BOM to accumulate manufacturing time and then work back based on current factory loading and capactities - which we don't currently hold any data for :-( So not really possible for manufactured items as it stands.

Phil Daintree
webERP Admin
Logic Works Ltd
http://www.logicworks.co.nz
Visit this user's website Find all posts by this user
Quote this message in a reply
Post Reply 


Messages In This Thread
Item Due Date - Jeff Harr - 03-10-2018, 02:00 AM
RE: Item Due Date - phil - 03-10-2018, 02:16 PM
RE: Item Due Date - Jeff Harr - 03-13-2018, 01:23 AM
RE: Item Due Date - VortecCPI - 03-13-2018, 03:14 AM
RE: Item Due Date - phil - 03-13-2018 04:58 AM
RE: Item Due Date - Jeff Harr - 03-13-2018, 06:17 AM

Forum Jump:


User(s) browsing this thread: 1 Guest(s)