webERP for ETO/MTO Environments
12-19-2017, 04:04 AM (This post was last modified: 12-19-2017 04:05 AM by VortecCPI.)
Post: #1
webERP for ETO/MTO Environments
Has anybody tried to use webERP for ETO/MTO Environments?

In this case a new Item must be created for each Job and a BoM specific to that new Item created and composed of standard Items kept in stock and/or Items purchased to suit.

I believe that could work but what happens after the Job is shipped and invoiced? Do we just set the top-level Item to Discontinued so it no longer shows since it will never be built again in the future?

If the top-level Item is set to Discontinued will the books still reflect everything properly or would the setting to Discontinued have to wait until after payment is received?

https://www.linkedin.com/in/eclipsepaulbecker
Visit this user's website Find all posts by this user
Quote this message in a reply
12-19-2017, 05:50 AM
Post: #2
RE: webERP for ETO/MTO Environments
Discontinued flag is really just to lose some of the chaff from item searches and try to minimise mistakes in input - in all other respects the item works like any other

Phil Daintree
webERP Admin
Logic Works Ltd
http://www.logicworks.co.nz
Visit this user's website Find all posts by this user
Quote this message in a reply
12-19-2017, 06:26 AM
Post: #3
RE: webERP for ETO/MTO Environments
Paul: Have you looked at the contracts functionality? This may do what you are looking for as it allows a BOM to be created specifically for a contract.

Phil: The obsolete stock options can be used in many other scenarios than just typing errors. It is common in many industries that a particular item is declared obsolete. I seem to remember Ricard did some work on substitute items as well for this
scenario.
Visit this user's website Find all posts by this user
Quote this message in a reply
12-20-2017, 03:24 AM (This post was last modified: 12-20-2017 03:28 AM by VortecCPI.)
Post: #4
RE: webERP for ETO/MTO Environments
(12-19-2017 06:26 AM)falkoner Wrote:  Paul: Have you looked at the contracts functionality? This may do what you are looking for as it allows a BOM to be created specifically for a contract.


No, I have not looked at that and thank you so much for bringing it to my attention. That is exactly the scenario in that the BoM is a one-time use. While it is possible it could be used in the future it is highly improbable it would.

On a side note... It looks as if webERP has better MRP functionality than ECi M1 ERP my customer just implemented.