Please someone help
This is the scenario.
I need to create a Bag with polyester as its main materials. This is what i did
1 Level - Bag (Manufactured) with BOM of Top Pocket and Mid Front Pocket
2 Level - Top Pocket (Phantom) with BOM of 0.02 meters of Polyester and Mid Front Pocket (Phantom) with BOM of 0.02 meters os Polyester
3 Level - Polyester (Purchased)
As you can see I need to cut the Polyester to create a material for my bag everything is smooth but once I create a Bag in Work Entry it always state that I only consumed 0.002 Polyester as a material. Which I'm expecting is 0.04 because of Top Pocket and Mid Front Pocket. Can someone help me to analyze this problem. Having a hard time to solve this.
Thanks.