prolem with WO and leadtime of purchased components
04-29-2012, 09:20 AM, (This post was last modified: 04-29-2012, 09:21 AM by opto.)
#4
RE: prolem with WO and leadtime of purchased components
which actually can be confirmed by the following:

create a BOM:

A: has AB, B

AB: has B, C.

create workorder for A.
Now there is demand for B from A and also from child AB.

Run Mrp calculation: for one demand of B, lead time is used, for the other, it is not.

If the planned WO for AB is converted, not lead time is used for B, because the component B which was on a lower level (or higher - I don't remember the definition) in A now moved its level after the WO for AB was created.

Maybe a specialist knows where to enter the leadtime for the toplevel components in levelnetting.

Klaus