STILL WRONG COSTS
10-02-2015, 10:04 PM,
#9
RE: STILL WRONG COSTS
I've set the standard cost for all items during the first installation in january 2015.

Now I've just found another negative cost.
   
I'm sure that it wasn't present in september, because I've checked all the
inventory for negative costs.

Looking at the movements there are no operations after july
   

Why the cost of this item is now negative?
There are procedure of cost maintainance running at scheduled intervals?
Reply


Messages In This Thread
STILL WRONG COSTS - by giusba71 - 09-28-2015, 09:55 PM
RE: STILL WRONG COSTS - by TimSchofield - 09-28-2015, 11:16 PM
RE: STILL WRONG COSTS - by giusba71 - 09-29-2015, 08:35 PM
RE: STILL WRONG COSTS - by TimSchofield - 09-30-2015, 01:23 AM
RE: STILL WRONG COSTS - by giusba71 - 09-30-2015, 05:32 PM
RE: STILL WRONG COSTS - by TimSchofield - 09-30-2015, 06:41 PM
RE: STILL WRONG COSTS - by giusba71 - 10-01-2015, 01:04 AM
RE: STILL WRONG COSTS - by Exsonqu_Qu - 10-02-2015, 11:07 AM
RE: STILL WRONG COSTS - by giusba71 - 10-02-2015, 10:04 PM
RE: STILL WRONG COSTS - by TimSchofield - 10-02-2015, 11:18 PM
RE: STILL WRONG COSTS - by agaluski - 10-02-2015, 11:00 PM
RE: STILL WRONG COSTS - by giusba71 - 11-04-2015, 05:40 PM
RE: STILL WRONG COSTS - by TimSchofield - 11-04-2015, 06:24 PM
RE: STILL WRONG COSTS - by giusba71 - 11-06-2015, 01:22 AM
RE: STILL WRONG COSTS - by TimSchofield - 11-06-2015, 06:29 PM
RE: STILL WRONG COSTS - by giusba71 - 11-13-2015, 05:45 PM
RE: STILL WRONG COSTS - by TimSchofield - 11-13-2015, 08:03 PM