convert WO after MRP calculation looses start date
04-13-2012, 05:08 PM, (This post was last modified: 04-13-2012, 05:14 PM by opto.)
#3
RE: convert WO after MRP calculation looses start date
Hi Exson,

thanks for your answer.

I had understood the MRP date to be the suggested start date.
If it is, it could be used to preset the start date in the converted WO.
I think MRP takes lead times into account and calculates date, so it would be helpful to transfer that to the WO.

I think to propose starting today does not make so much sense. What would really help woul b to propose the latest possible start date based on lead times, then I know I can shift it from future towards today, but also know I must not start later than that date if I want to complete in time.

Klaus