RE: 4.07.6 WO does not do costing properly
if i understand correctly, say 1 nut and 1 bolt makes a product, so if nut cost $1 and bolt cost $2, assume no labour cost etc, the end product will come out with a standard cost of $3.
In a closed system, if the erp system only have 1 nut and 1 bolt before the wo, the whole erp is worth $3, after the wo, there is zero nut and zero bolt and 1 end product, whole erp is still $3.
Now the before and after does not tie up. simple as that.
i manufacture 1 item to 1 item, you can assume that i have a blue nut, and i paint it red to make it a red one, assume not cost of labour or paint, i am really using it to "convert stocks" to move items between colours or attribute.
i think i phrase it wrong when i say update costing, we just click on the costing to receive the raw material or sometimg, just the standard WO process, we dont do any manual adjustment anywhere.
|