TRANSFER ITEMS FROM INVENTORY LOCATION TO PRODUCTION - petero@laballieds - 01-27-2016

Hi guys, op you are fine, my business requires me to transfer items from warehouse to a workcenter for production, We want to control this from inventory(warehouse ) so we issue a delivery note and production people will receive using a receive note, How can i accomplish this in weberp, i was thinking of creating another virtual production location(warehouse) so they can transfer to them but how will this link with workcenters.Or any alternative suggestion?

Peter
I am aware there is a transfer note from warehouse to warehouse but i want a transfer note from warehouse to workcenters.


RE: TRANSFER ITEMS FROM INVENTORY LOCATION TO PRODUCTION - falkoner - 01-27-2016

Each work centre has a location attached to it so you could attach your "virtual production location" to the work centre and transfer the stock there.

Tim


RE: TRANSFER ITEMS FROM INVENTORY LOCATION TO PRODUCTION - petero@laballieds - 02-01-2016

Thanks Falkoner it worked
There isa question my Boss has raised the present system Sage Pastel allows one to setup a component in the BOM more than once ie the same component with different quantities what is the effect if i can allow the same in weberp


RE: TRANSFER ITEMS FROM INVENTORY LOCATION TO PRODUCTION - falkoner - 02-01-2016

There would be repercussions in the work order processes, but I would have to go back and remind myself exactly what would need to be done.

Thanks
Tim


RE: TRANSFER ITEMS FROM INVENTORY LOCATION TO PRODUCTION - petero@laballieds - 02-01-2016

oK thats fine lem wait for you Falkoner will real appreciate your reply, i feel the same i think the best thing is to add accumulated quantities of each component to the BOM, since they need different quantities of a component at each stage in a multistage processing then we can issue this quantites to work order in different quantities. The problem now becomes if i need a report of the original BOM quantities?